Completed Operations Is Not an Exclusion, and That Confusion Costs Money

Search for the phrase and half the results will tell you the CGL policy excludes completed operations. It does not. Two separate things share a nickname, and the mix-up produces both bad contracts and rejected certificates.

Covered, but on a separate aggregate

A commercial general liability policy covers injury or damage that happens while the named insured's work is being performed. It also covers injury or damage that happens afterward, away from the site, arising out of that finished work or a product. The second bucket is the products-completed operations hazard, and it carries its own aggregate limit in the declarations.

So the coverage exists. The question is always whether it exists on this policy and whether it reaches this additional insured.

What people actually mean by "the exclusion"

Two clauses get called that.

The first is damage to your work. If a subcontractor's own finished work is defective and has to be torn out and redone, the policy does not pay for the redo. That is the contractor's warranty obligation, not a covered loss. Every policy has some version of this clause and it is normal.

The second is a completed-operations exclusion endorsement, which some carriers attach for roofing, residential, or other high-hazard work. That one removes the hazard or narrows it, and it is the reason a certificate gets bounced.

The first gets shrugged at. The second should not be.

Two ways a certificate fails on this

A reviewer looks at the products-completed operations aggregate on the certificate and then at the declarations behind it. Blank or zero means the hazard has been removed or never existed, and the GC's future claims have nothing behind them.

The other failure is subtler. The hazard is intact, the aggregate is healthy, and the additional insured endorsement covers ongoing operations only. CG 20 10 on its own is exactly that. The coverage exists, the GC is simply not an insured under the part of it that matters two years from now.

Nothing on the ACORD 25 distinguishes that from an adequate file. The additional insured box is checked either way.

Why the timing matters

Defects surface late. A crew finishes in spring, the policy renews in summer, the failure shows up as water staining or a cracked slab the following year. By then the subcontractor may be insured somewhere else, insured nowhere, or gone.

The GC's own exposure did not end when the work did. Their completed-operations coverage is what sits between a defect claim and their balance sheet, which explains why the insurance exhibit asks for completed operations additional insured status in the first place.

Reading the file

Start with the declarations page. The products-completed operations aggregate should be present, non-zero, and in most construction programs equal to the general aggregate.

Then the endorsement. It should name the project entity and reach completed operations, through CG 20 37, CG 20 38, or a manuscript equivalent.

Then the edition date in the footer, because the scope language moved between editions and the date is the only reliable marker.

Then the subcontract. An exhibit that says additional insured and stops there is an exhibit that will be argued about at claim time. The useful phrasing names ongoing and completed operations separately.

Then the umbrella, if there is one. A $5M requirement backed by a $1M primary means the excess carrier also needs to grant additional insured status and completed operations. Otherwise the layer above the primary is not available to the GC, whatever the certificate total says.

What changes by carrier and state

Residential construction, roofing, and work above a certain height are where completed-operations exclusions and sublimits concentrate. A program written for tenant improvements can exclude precisely the scope in the contract.

Some carriers want a separate completed-operations endorsement on top of the standard additional insured form. Others write one proprietary form covering both phases.

Statutes of repose and limitation periods vary by state and determine how long a defect claim can be brought at all, which determines how long coverage needs to stay in force. That is a question for counsel in the relevant state.

And the definition of your work includes work performed by subcontractors on the named insured's behalf. Reviewing a sub-subcontractor's policy means following a longer definition chain than most reviewers expect.

Related: CG 20 10 vs. CG 20 37 and subcontractor insurance requirements by trade.