What GCs Ask Subcontractors to Carry, Trade by Trade
A roofer and a painter do not get the same insurance exhibit. Not because anyone wrote a law about it, but because a GC sets limits according to what tends to go wrong on that scope of work.
Knowing the pattern is useful in both directions. It tells a subcontractor quickly whether a requirement is ordinary or aggressive, and it tells a GC whether their own exhibit makes sense.
The four lines everything starts from
General liability, auto liability, workers compensation, umbrella or excess. Limits move with the trade. The additional insured scope and completed operations language tend to be identical across trades, and that is where the surprises live.
A reasonable floor for light commercial work looks like this: $1M per occurrence and $2M general aggregate on general liability, $1M combined single limit auto, statutory workers compensation with $1M employer's liability, additional insured for ongoing and completed operations, waiver of subrogation on both the liability and workers comp policies, thirty days notice of cancellation. Requirements below that floor usually get rejected. Anything above it is negotiation.
Where each trade differs
| Trade | Typical GL limits | Extra lines commonly required | The trap |
|---|---|---|---|
| Roofing | $1M / $2M, often $2M / $4M | Umbrella, more often than any other trade | Completed operations AI status is frequently excluded by the carrier for roofing |
| Excavation / sitework | $1M / $2M, frequently $2M / $4M | Auto for hauling, sometimes environmental | Owned, hired, and non-owned auto gets missed, and haul-off liability sits on the auto policy |
| Electrical | $1M / $2M | Umbrella on larger scopes | Completed operations claims arrive years later, and CG 20 10 alone leaves the GC outside them |
| Mechanical / HVAC | $1M / $2M | Umbrella, sometimes professional for design-build | Design-build scope needs professional liability, which no general liability certificate covers |
| Concrete | $1M / $2M | Umbrella | Structural failures are completed operations claims, so a blank aggregate is the thing to catch |
| Painting / drywall / finishes | $1M / $2M | None usually | Limits get relaxed, AI and waiver requirements do not |
| Landscaping | $1M / $2M | Auto for trucks and trailers | Same auto gap as excavation, plus hired and non-owned coverage for equipment trailers |
| Janitorial / service | $1M / $2M | Bonding, sometimes crime | Workers comp is the live exposure, so make sure statutory limits are actually displayed |
| Trucking / material supply | $1M CSL auto | Cargo, sometimes pollution | A general liability certificate says nothing about auto liability, which is the entire exposure |
| Abatement / hazmat | $1M / $2M | Pollution liability required | The CGL policy has a pollution exclusion, so a clean certificate can still leave the GC exposed |
Why the numbers move
These are contract ranges, not statutes. No state requires a $2M aggregate from an electrician. The contract, the owner's requirements, and the GC's own carrier each push the figure.
Owner-imposed requirements flow downhill. When a project has a construction lender or an institutional owner, the GC's exhibit is often a copy of the owner's list, which can be stricter than the GC would have chosen alone.
Workers compensation is statutory nearly everywhere, and a few states, Texas among them, let employers opt out with prescribed notice. A Texas certificate with no workers comp line may be legitimate. The same certificate in most other states is a defect.
Residential work is priced and excluded differently from commercial work. A subcontractor with a strong commercial program can carry no residential completed operations coverage at all, and the certificate will not announce it.
Endorsements cost money. A carrier willing to grant completed operations status on roofing charges for it, and the subcontractor who priced the job before that requirement appeared may not have it.
Reading your own exhibit
An exhibit that treats every trade the same is either over-insuring the painters or under-insuring the roofers, and both show up as money.
For a subcontractor, the exhibit states which lines and which additional insured scope will be requested. Those are the terms worth confirming with an agent before signing. Additional insured for ongoing and completed operations, waiver of subrogation on liability and workers comp, thirty days notice: an agent can price that in a single phone call. Finding out after award is how projects stall.